5 januari 2012
Tight Stow for the Jumbo Javelin
Jumbo has transported two Ship-to-Shore Kalmar cranes, combined with a total of seven knocked down RTG’s from Taicang, China, to Cartagena, Colombia, for Cargotec. Since the STS cranes were too big to handle in their fully assembled shape, both cranes were shipped in parts to fit Jumbo Javelin’s deck and cargo hold. Visit the photo album for more pictures of the operation.
The crane structures, weighing up to 1,000 t per piece, reached 80 m above deck and protruded 30 m on starboard side of the vessel. The lower portal and upper structure of the first crane were lifted and placed on deck separately. The complete middle piece of the second crane was lifted on deck at once in a tandem lift.