February 5, 2015
Seaway Installs Four Topsides and a Jacket in the Gulf of Mexico

(With extra pictures) Seaway Heavy Lifting’s crane vessel Oleg Strashnov has installed the last three topsides in one week for client Protexa/Pemex.

Out of a string of jackets and topsides in the Gulf of Mexico the last topside was installed on Wednesday 28 January at 07.15am local time. The project location was the Bay of Campeche in the Gulf of Mexico.

Below extra pictures of Seaway's project. Please click the pop-out link (the little squares at the bottom right) to view them in their proper dimensions.

Picture above: Placing the Kab-C 1800 Mt topside, 3 December 2014.

The Tsimin-D 2033 Mt topside, 28 January 2015KU-B 2,800Mt topside, 26 January 2015Ayatsil-D 3130 Mt topside, 21 January 2015Kuil-B 1430 Mt jacket, 29 December 2014